Permitting and Drilling Rig

Preparatory work is continuing in Cuba in readiness for the planned drilling program in Block 9. From a permitting perspective, intermediate approvals are continuing to be obtained for both theAlameda and Zapato exploration wells as progress is made towards submissions for the final Approval to Drill permits.

Civil works contract scope definition has progressed and the civil works tender evaluation for the Alameda-1 drilling pad was completed and the preferred contractor identified. Melbana’s Cuba based team has undertaken a number of site visits and community liaison sessions to support potential civil works.

Preferred contractor has been identified and discussions are continuing with the preferred drilling rig provider, which is an established local entity, with a drilling rig being identified and a drilling window nominated as notionally commencing in December 2018. The proposed rig is currently planned to be refurbished and upgraded for maintenance and operational purposes in late 3Q 2018. The final decision on drilling contractor, drilling target and timing will be influenced by a number of factors, including any incoming party into Block 9 and their plans, their preferred drilling targets and confirmation of drilling rig availability.

Farm out

Block 9 farmout activities are continuing, with multiple interested multinational parties engaged in assessing the prospectivity of the Block.

A short video on Cuba Block 9 is available on the Melbana website (melbana.com) under News and Broadcasts / Broadcasts and Videos.

Photo - see caption

Block 9 PSC with high graded drilling targets

Check out our other current stories, we dare you…

——Want to connect with people like you?——

Do you have questions that only a professional can answer, download the app and connect with them!

Download it free here today!

Comments (0)

Leave Comment


Check out our other stories

Rig Lynx
Mar 09, 2023

  Valaris Limited announced new contracts awarded subsequent to issuing the Company’s most recent fleet status report on February 21, 2023.   Three-year contract with Petrobras for drillship VALARIS DS-8. The rig will be reactivated for this contract. The total contract value is approximately $500 million, including a $30 million mobilization fee. 100-day contract with a TotalEnergies affiliate for drillship VALARIS DS-12. The contract is expected to commence in second quarter 2023. 70-day contract with Beach Energy offshore New Zealand for heavy duty modern jackup VALARIS 107. The contract is expected to commence in third quarter 2023. The total contract value is approximately $26 million. President and Chief Executive Officer Anton Dibowitz said, “We are particularly pleased to have secured the award for preservation stacked drillship VALARIS DS-8, for a contract that is expected to generate a meaningful return over the firm contract term, and we remain focused on exercising our operational leverage in a disciplined manner. This most recent award represents the sixth contract awarded to one of our high-quality stacked floaters since mid-2021, and speaks volumes about our demonstrated track record of project execution when reactivating rigs.”   Dibowitz added, “Following the reactivation of VALARIS DS-17 and DS-8, we will have ten floaters working across the golden triangle, including four drillships in Brazil, a market where we expect to see continued growth over the next several years.”   Updated Guidance   As a result of the contract awarded to VALARIS DS-8, which will require the rig to be reactivated from preservation stack, we are updating our first quarter 2023 and full-year 2023 guidance provided on our fourth quarter 2022 conference call on February 21, 2023.   First Quarter 2023   Contract drilling expense is expected to increase by approximately $5 million to $385 million to $395 million. Adjusted EBITDA is expected to decrease by approximately $5 million to negative $5 million to breakeven. Adjusted EBITDAR, which adds back one-time reactivation expense, is expected to be $25 million to $30 million, unchanged from the guidance provided on our fourth quarter 2022 conference call. Full-Year 2023   Revenues are anticipated to be $1.8 billion to $1.9 billion, unchanged from the guidance provided on our fourth quarter 2022 conference call. Contract drilling expense is expected to increase by approximately $60 million to $1.49 billion to $1.59 billion. Adjusted EBITDA is expected to decrease by approximately $60 million to $180 million to $220 million. Adjusted EBITDAR, which adds back one-time reactivation expense, is expected to be $280 million to $320 million, unchanged from the guidance provided on our fourth quarter 2022 conference call. Capital expenditures are expected to increase by $60 million to $320 million to $360 million. Source: Valaris Join our mailing list here We are #1 on Google and Bing for the "Largest Mobile Energy Network" Come join our community! Download the Rig Lynx app here  

Rig Lynx
Mar 09, 2023

  Seadrill Limited announced that the West Neptune has executed approximately six months of term extensions with LLOG Exploration Offshore, L.L.C in the US Gulf of Mexico.   The extensions will commence in direct continuation of the existing term, and will keep the rig busy until Q3 2024, furthering Seadrill and LLOG’s long-term association. Total contract value for the extension is approximately $79 million. Source: Seadrill   Join our mailing list here We are #1 on Google and Bing for the "Largest Mobile Energy Network" Come join our community! Download the Rig Lynx app here  

Rig Lynx
Mar 09, 2023

  Semisub rig owner Dolphin Drilling has inked a new contract with Peak Petroleum in Nigeria for its 1974-built Blackford Dolphin.   The firm contract, which follows the letter of award in January, gives the Euronext Growth-listed owner of three rigs the potential to extend the unit’s backlog by a minimum of 120 days and up to 485 days. The deal adds to and will be a direct continuation of the previously announced 12-month contract with General Hydrocarbon Limited (GHL).   Øystein Stray Spetalen-backed company said the effective dayrate associated with the minimum firm period of the contract is $325,000, including the mobilisation fee.   “The final award of the contract for Blackford Dolphin shows the opportunities in Nigeria at a strong dayrate, in addition to building on the backlog for the rig. It also underlines the attractiveness of our assets, and we look forward to returning to revenue-generating operations in 2023,” noted Bjørnar Iversen, CEO of Dolphin Drilling.   Source: Dolphin   Join our mailing list here We are #1 on Google and Bing for the "Largest Mobile Energy Network" Come join our community! Download the Rig Lynx app here